Complete Streets

Complete Streets

o   Sudbury Road Crosswalk at Seven Star Lane

Allied Paving Corporation mobilized during the last week of August and has since brought the project to substantial completion as of the first week of October. The crosswalk, including the rectangular rapid flashing beacons are fully operational.

o   Hubbard St. and Stow St. Parking Lot

The drainage improvements along Hubbard St. and in the Stow St. parking lot were completed in the fall of 2021.  The Water and Sewer Division has also completed their sewer-lining project. Newport Construction is scheduled to remobilize the 2nd week of April to start the road reclamation, paving and installation of the sidewalks. The majority of this work is tentatively scheduled to be complete in May.   

o   Commonwealth Ave

The project is currently out for bid with the 2022 Roadway Improvements Project.  Once a contractor is selected, a schedule will be developed.  Construction is preliminarily planned to start in June 2022. CMLP and National Grid have some utility work that will need to be performed prior to any roadway and sidewalk construction. Their work is planned to begin at the end of April 2022.

 Town Contact::

Justin Richardson, PE, Assistant Town Engineer, Concord Public Works – Engineering Division, 978-318-3210, Jrichardson@concordma.gov