“ Roadway Improvement Program - Patch Repairs”- 04/30/18
Please be advised that the Town’s contractor for the Roadway Patch Repair Program, Lazaro Paving, will be completing patch repairs along various streets including, Walden Street, Pine St, Kenny Dunn Sq., and Barrett’s Mill Rd. The first stage of the project will consist of milling the top course of pavement within the designated patch areas followed by paving the milled areas with asphalt pavement. This project is expected to take 2-3 weeks to complete, weather permitting. Traffic interruptions will be minimal.
Please proceed with caution through these work zones. Expect localized delays near the construction crews and seek alternate routes, if possible. For more information and scheduling please contact the CPW- Engineering Division 978-318-3210.