Please be advised that drainage work inside the paved roadway surface is planned to commence on Thursday, October 20th, 2022, at 8:00 AM. The work will be adjacent to Sawmill Brook (close to #1061 Monument Street).
The work will entail partial closure of the above-mentioned street, however one-way alternating traffic will be maintained through the construction zone.
Heavy equipment will be present and operational. Access to all properties will be maintained throughout the construction process, however, please expect minor delays near construction crews performing the work.
For more information, please contact the CPW- Engineering Division 978-318-3210.