Sleepy Hollow Cemetery Roadway

Project:

Contract # 2140 - SleepyHollow Cemetery Roadway Reconstruction – Phase II


Town Contact:

Nathan Chin, Assistant PublicWorks Engineer, Concord Public Works – Engineering Division, 978-318-3210, nchin@concordma.gov


General Contractor:

Sunshine Paving Corporation,North Chelmsford, Massachusetts


Project Background:

Phase II of the RoadwayReconstruction project is a continuation of an overall multi-year improvementproject for the historic Sleepy Hollow Cemetery to improve deterioratingroadway and drainage infrastructure.  This phase will includeapproximately 1,350 linear feet of new drainage pipe and 400 linear feet ofriver stone lined waterways constructed to address roadway flooding on thecemetery grounds.  In addition, 3,700 linear feet of cemetery roadway willbe reclaimed, re-graded and re-paved. 


Project Schedule:


Below is the project scheduleof work to be performed.  Please note that this schedule is subject tochange.

7/5 –7/6         Mobilization of equipment,material, tree protection installation and silt bags

7/6 – 7/13      Drainage infrastructure installation

7/16                Cemetery roadway milling

7/17 –7/18     Excavate road sub-base (in selected areas, asneeded)

7/19 –7/25     Install road sub-base and fine grade the site

7/26                Install hot mix asphalt binder course

7/27                Install drainage structure castings

7/30 –8/3       Install river stone waterway

8/6                  Install granite curbing and bollards

8/7                  Plantings

8/8 –8/10       Loam and seed disturbed areas andgeneral site clean-up

8/13                Install hot mix asphalt top course